We decided to put some ledgestone on the foundation of the house, so we figured it would look good to put a little in the interior as well. We installed some ledgestone on the bar side of the kitchen island and below the jacuzzi tub.
November 7, 2011 - Monday
Began stone work on exterior. The stone is Veneerstone (Verago) from Home Depot.
Finished all concrete and gravel work.
November 8, 2011 - Tuesday
Formed gate supports. We aren't planning on putting up a gate right away, but will put up the supports since we have enough stone.
November 9, 2011 - Wednesday
Continued stone work.
November 10, 2011 - Thursday
Continued stone work.
November 11, 2011 - Friday
Continued stone work - around the BBQ area.
November 12, 2011 - Saturday
Finished stone work. Put on Stone caps
November 23, 2011 - Wednesday
Finsihed caulking stone. Hooked up the BBQ.
I'll have to add pictures later. It's been raining and it is a muddy mess. Once I get it somewhat landscaped I will take some pictures.
WE ARE OFFICIALLY COMPLETED!!!