Comfort Flow Heating and Air began installing the furnace and assembling all the ductwork for the HVAC system (Trane). They were here several weeks ago putting in ductwork in the crawlspace, now they are putting in the rest. This will proabably take a few days. They will be here again toward the end of construction to complete the system and get it online.
June 20, 2011 - Monday
Started installing ductwork throughout the house.
June 21, 2011 - Tuesday
Continued to install ductwork throughout the house.
Started framing soffits around some of the ducting
June 22, 2011 - Wednesday
Finished installing ductwork. Installed vents for bath fans and range hood. Installed propane supply line for range.
Finished soffits and other framing around HVAC and ducting.
June 29, 2011 - Wednesday
Passed our HVAC and propane line inspection. Comfort flow will return when the house is nearing completion.
October 11, 2011 - Tuesday
The guys from Comfort Flow are back to complete the HVAC. Installed vents, thermostats and everything necessary to complete the HVAC system. Works great.